Monsanto: Packaging Approvals Cut From Months to Days

Case Study

Monsanto Agricultural Group coordinated 500 packaging items across 15 locations worldwide with a twelve-step approval process that took two or three months. Keene Systems’ PC-Specs software linked the offices and cut that to two or three days, a reduction of 97%.

This case study appeared in Package Engineering Magazine.

About Monsanto Agricultural Group

Monsanto Agricultural Group serves farmers, landscapers and homeowners from 15 locations around the world, and manages some 500 packaging SKUs across them.

The problem

Even with a company-built database and hard-copy backup, the group had its hands full. The approval process involved 12 sequential steps, said Mike Stoppleman, Monsanto’s purchasing manager. Documents were passed around headquarters and the plants, and could be delayed for days at any step. A package designer who wanted to check progress found it hard even to locate the documents.

The delay had real costs. Plant managers could order packaging components that were no longer used or were the wrong size. Worse, the introduction of a new package or product could be held up.

The solution

Stoppleman suggested packaging software that could be networked to connect all of the group’s locations in real time. Monsanto chose Keene Systems’ PC-Specs.

  • From sequential to concurrent approval. A finished specification goes electronically to every manager in the first round of approvals at once. When they have adjusted and approved it, the software alerts the next tier automatically.
  • Designers enter their own work. Specifications go straight into the system with CAD drawings, graphics and text. That removes the clerical errors of re-keying and lets designers review each other’s work before it goes out.
  • A chance to clean house. Monsanto used the conversion to standardize its specification form, retire obsolete specifications and correct others.
  • A format that can change. New fields and layouts can be added as packaging information needs change.

Results

  • Packaging approval time fell from two or three months to two or three days.
  • Nobody has to track down where a specification is.
  • Information for other needs is on hand. A plant manager who needed a large amount of data for an ISO 9000 certification program was amazed to find it could be printed at the push of a button.

What the client said

The need to keep track of a spec is gone. There will be a need for some follow-up using electronic mail, but with the return-and-reply capabilities, our turnaround time is no more than five days.

Mike Stoppleman, Purchasing Manager, Monsanto Agricultural Group

The same problem today

This project dates from the era of office networks and dial-up connections, and the technology has moved on. The problem has not. Approvals still move one desk at a time, and offices in different places still work from different copies. Today Keene Systems solves it with a web application that every department, plant and supplier reaches from a browser. See one system for every division and moving a paper process into software.

Have a project like this one? Schedule a project exploration call or use the form at the bottom of this page.